BED STUY CENTRAL AND NORTH PHASE II

772 MYRTLE AVENUE (Boro: 3, Block: 1754, Lot: 16)
Brooklyn

Duration

Total Duration:7.4 years
Start Date:Nov 2017
End Date:Apr 2025

Identifiers

Project ID:68222
Building ID:1005398

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
201720182019202020212022202320242025ActualOfficialBED STUY CENTRAL AND NORTH PHASE...772 MYRTLE AVENUE(Boro: 3, Block: 1754, Lot: 16)Brooklyn8.1+yrs2.0+yrs

Timeline Events (8)

Nov 27, 2017
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_18HPD093K] Earliest EAS Work (Phase I ESA)
Nov 22, 2019
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_18HPD093K] Lead Agency Letter
Feb 24, 2020
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_18HPD093K] EAS Date
Mar 05, 2020
✅ Udaap Designation + Disposition City Owned Property [2018K0517] Negative Declaration
Mar 05, 2020
✅ Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_18HPD093K] Negative Declaration
Oct 21, 2021
Earliest DOB Filing
Dec 12, 2023
HPD Financing ("Project Start")
Apr 15, 2025
Fully Permitted