MOSAIC

1717 LINCOLN PLACE (Boro: 3, Block: 1474, Lot: 65)
Brooklyn

Duration

Total Duration:32.4 years
Start Date:Apr 1992
End Date:Aug 2024

Identifiers

Project ID:68467
Building ID:1002283

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
199219962000200420082012201620202024ActualOfficialMOSAIC1717 LINCOLN PLACE(Boro: 3, Block: 1474, Lot: 65)Brooklyn33.8+yrs2.0+yrs

Timeline Events (11)

Apr 01, 1992
Zoning Map Amendment + Disposition City Owned Property [NO_ZAP_92HPD008K] Earliest EAS Work (Historic Resources Review)
Jun 18, 1992
Zoning Map Amendment + Disposition City Owned Property [NO_ZAP_92HPD008K] Lead Agency Letter
Aug 05, 1992
Zoning Map Amendment + Disposition City Owned Property [NO_ZAP_92HPD008K] EAS Date
Aug 27, 1992
✅ Zoning Map Amendment + Disposition City Owned Property [NO_ZAP_92HPD008K] Negative Declaration
Sep 01, 2006
Disposition City Owned Property + Udaap Designation [NO_ZAP_10HPD022K] Earliest EAS Work (Phase I ESA)
Mar 26, 2010
Disposition City Owned Property + Udaap Designation [NO_ZAP_10HPD022K] Lead Agency Letter
Apr 26, 2010
Disposition City Owned Property + Udaap Designation [NO_ZAP_10HPD022K] EAS Date
Apr 26, 2010
✅ Disposition City Owned Property + Udaap Designation [NO_ZAP_10HPD022K] Negative Declaration
Sep 08, 2021
Earliest DOB Filing
Dec 21, 2023
HPD Financing ("Project Start")
Aug 26, 2024
Fully Permitted