THE BARNETT
50-25 BARNETT AVENUE (Boro: 4, Block: 119, Lot: 143)
Queens
Duration
Total Duration:17.0 years
Start Date:Jul 2007
End Date:Jul 2024
Identifiers
Project ID:65369
Building ID:1002282
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (14)
Jul 01, 2007
Zoning Map Amendment + Zoning Text Amendment + Funding Programs (Contemplated) [P2014Q0465] Earliest EAS Work (Phase I ESA)
Jul 01, 2007
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2017Q0346] Earliest EAS Work (Phase I ESA)
Aug 10, 2011
Other Discretionary Permit [NO_ZAP_12TLC005Q] Lead Agency Letter
Aug 10, 2011
Other Discretionary Permit [NO_ZAP_12TLC005Q] EAS Date
Aug 10, 2011
✅ Other Discretionary Permit [NO_ZAP_12TLC005Q] Negative Declaration
Jan 07, 2016
Zoning Map Amendment + Zoning Text Amendment + Funding Programs (Contemplated) [P2014Q0465] Lead Agency Letter
Mar 25, 2016
Zoning Map Amendment + Zoning Text Amendment + Funding Programs (Contemplated) [P2014Q0465] EAS Date
Mar 28, 2016
✅ Zoning Map Amendment + Zoning Text Amendment + Funding Programs (Contemplated) [P2014Q0465] Negative Declaration
Oct 01, 2019
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2017Q0346] Lead Agency Letter
Oct 02, 2020
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2017Q0346] EAS Date
Oct 02, 2020
✅ Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2017Q0346] Negative Declaration
Feb 16, 2022
Earliest DOB Filing
Jun 26, 2024
HPD Financing ("Project Start")
Jul 03, 2024
Fully Permitted