PENINSULA A1
5123 BEACH CHANNEL DRIVE (Boro: 4, Block: 15843, Lot: 7501)
Queens
Duration
Total Duration:8.1 years
Start Date:Jul 2016
End Date:Aug 2024
Identifiers
Project ID:65303
Building ID:1001190
Data Quality Note
37-48 (Good)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (10)
Jul 28, 2016
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) + Hpd Hdc Program Funding (Contemplated) [2021Q0310] Earliest EAS Work (Site Survey)
Mar 15, 2018
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) + Hpd Hdc Program Funding (Contemplated) [2021Q0310] EAS Date
Mar 15, 2018
⚠️ Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) + Hpd Hdc Program Funding (Contemplated) [2021Q0310] Positive Declaration (EIS Required)
Mar 16, 2018
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) + Hpd Hdc Program Funding (Contemplated) [2021Q0310] Lead Agency Letter
Mar 16, 2018
⚠️ City Map Amendment + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Zoning Special Permit Cpc [P2016Q0306] Positive Declaration (EIS Required)
Oct 19, 2020
Earliest DOB Filing
Dec 16, 2021
HPD Financing ("Project Start")
Feb 24, 2022
Fully Permitted
Aug 28, 2024
Building Completion (HPD)
Aug 29, 2024
Certificate of Occupancy