168TH STREET GARAGE

92-23 168 STREET (Boro: 4, Block: 10209, Lot: 7501)
Queens

Duration

Total Duration:6.7 years
Start Date:Feb 2015
End Date:Oct 2021

RFP Information

168th Street Garage RFP

Identifiers

Project ID:63761
Building ID:1000088

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20152016201720182019202020212022202320242025ActualOfficial168TH STREET GARAGE92-23 168 STREET(Boro: 4, Block: 10209, Lot: 7501)Queens6.7yrs3.3yrs

Timeline Events (11)

Feb 13, 2015
RFP Release: 168th Street Garage RFP
Jan 26, 2017
✅ RFP Designation: 168th Street Garage RFP
Apr 19, 2017
Disposition City Owned Property + Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_17DME003Q] Earliest EAS Work (Industrial Source Survey)
Jun 09, 2017
Disposition City Owned Property + Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_17DME003Q] Lead Agency Letter
Jun 09, 2017
Disposition City Owned Property + Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_17DME003Q] EAS Date
Jun 09, 2017
✅ Disposition City Owned Property + Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_17DME003Q] Negative Declaration
Aug 07, 2017
Earliest DOB Filing
Jun 29, 2018
HPD Financing ("Project Start")
Apr 08, 2019
Fully Permitted
Oct 14, 2021
Building Completion (HPD)
Oct 14, 2021
Certificate of Occupancy